uitloop werkzaamheden

Over-running engineering works: Breda-Eindhoven; Breda-'s-Hertogenbosch (26 September 2021)

  1. Disruption resolved Last update

    Between Gilze-Rijen and Tilburg the train traffic is fully resumed.

  2. Delays decreasing

    Between Gilze-Rijen and Tilburg the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 AM hours.

    Advice

    Local buses are still running between Gilze-Rijen, Tilburg Reeshof, Tilburg Universiteit and Tilburg.

  3. Update

    Between Gilze-Rijen and Tilburg no trains are running due to over-running engineering works.
    This will take until approximately 10:00 AM hours.

    Advice

    Local buses are running between Gilze-Rijen, Tilburg Reeshof, Tilburg Universiteit and Tilburg.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Breda and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Gilze-Rijen and 's-Hertogenbosch
  4. Update

    Between Gilze-Rijen and Tilburg no trains are running due to over-running engineering works.
    This will take until approximately 9:15 AM hours.

    Advice

    Local buses are running between Gilze-Rijen, Tilburg Reeshof, Tilburg Universiteit and Tilburg.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Breda and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Gilze-Rijen and 's-Hertogenbosch
  5. Update

    Between Gilze-Rijen and Tilburg no trains are running due to over-running engineering works.
    This will take until approximately 9:15 AM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Breda and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Gilze-Rijen and 's-Hertogenbosch
  6. Update

    Between Gilze-Rijen and Tilburg Universiteit no trains are running due to over-running engineering works.
    This will take until approximately 9:15 AM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Breda and Tilburg
    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between Breda and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. is cancelled between Gilze-Rijen and 's-Hertogenbosch
  7. Update

    Between Gilze-Rijen and Tilburg no trains are running due to over-running engineering works.
    This will take until approximately 9:15 AM hours.

  8. Disruption

    Between Breda and Tilburg there is a service disruption due to over-running engineering works.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 7:11 AM on September 26, 2021 and took 2 hours, 18 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.