Damaged railway bridge:
Utrecht-Rotterdam; Utrecht-Rotterdam; Breukelen-Rotterdam (30 August 2021)
Current status:
This disruption is resolved.
Disruption resolved
Last update
Between Rotterdam Centraal and Rotterdam Noord the train traffic is fully resumed.
Between Utrecht Centraal and Rotterdam Centraal the train traffic is fully resumed.
Between Utrecht Centraal and Rotterdam Centraal the restrictions are resolved.
Between Rotterdam Centraal and Rotterdam Noord the restrictions are resolved.
Delays are decreasing.
Service is normal around 5:15 PM hours.
Update
Between Rotterdam Centraal and Rotterdam Noord no trains are running due to a damaged railway bridge.
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
Service is normal around 5:15 PM hours.
Advice
Use the RET tram around Rotterdam between Rotterdam Noord and Rotterdam Centraal.
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Train measures
Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Rotterdam Noord and Rotterdam Centraal
Sprinter 7700 Rotterdam C. - Goverwelle is cancelled between Gouda Goverwelle and Rotterdam Centraal
Update
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
Between Rotterdam Centraal and Rotterdam Noord no trains are running due to a damaged railway bridge.
This will take until approximately 5:45 PM hours.
Advice
Use the RET tram around Rotterdam between Rotterdam Noord and Rotterdam Centraal.
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Train measures
Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Rotterdam Noord and Rotterdam Centraal
Sprinter 7700 Rotterdam C. - Goverwelle is cancelled between Gouda Goverwelle and Rotterdam Centraal
Update
Between Rotterdam Centraal and Rotterdam Noord no trains are running due to a damaged railway bridge.
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
This will take until approximately 5:45 PM hours.
Advice
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Train measures
Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Rotterdam Noord and Rotterdam Centraal
Sprinter 7700 Rotterdam C. - Goverwelle is cancelled between Gouda Goverwelle and Rotterdam Centraal
Update
Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
Between Rotterdam Centraal and Rotterdam Noord no trains are running due to a damaged railway bridge.
This will take until approximately 5:15 PM hours.
Advice
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Train measures
Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Rotterdam Noord and Rotterdam Centraal
Sprinter 7700 Rotterdam C. - Goverwelle is cancelled between Gouda Goverwelle and Rotterdam Centraal
Update
Between Rotterdam Centraal and Rotterdam Noord no trains are running due to a damaged railway bridge.
This will take until approximately 5:15 PM hours.
Advice
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Train measures
Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Utrecht Centraal and Rotterdam Centraal
Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Rotterdam Noord and Rotterdam Centraal
Sprinter 7700 Rotterdam C. - Goverwelle is cancelled between Gouda Goverwelle and Rotterdam Centraal
Update
Between Rotterdam Centraal and Rotterdam Noord no trains are running due to a damaged railway bridge.
This will take until approximately 5:15 PM hours.
Advice
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Update
Between Rotterdam Noord and Rotterdam Centraal no trains are running due to a damaged railway bridge.
This will take until approximately 5:15 PM hours.
Advice
Passengers between Rotterdam Centraal and Gouda and Utrecht Centraal travel via Den Haag Centraal. The extra travel time is more than 30 minutes.
Update
Between Rotterdam Noord and Rotterdam Centraal no trains are running due to a damaged railway bridge.
This will take until approximately 5:15 PM hours.
Update
Between Rotterdam Alexander and Rotterdam Centraal there is a service disruption due to a damaged railway bridge.
Updates will follow as more information becomes available.
Disruption reported
Between Rotterdam Centraal and Rotterdam Alexander there is a service disruption due to a damaged railway bridge.
Updates will follow as more information becomes available.