uitloop werkzaamheden

Over-running engineering works: Dordrecht-Breda; Dordrecht-Roosendaal (18 August 2021)

  1. Disruption resolved Last update

    Between Dordrecht and Lage Zwaluwe the train traffic is fully resumed.

  2. Delays decreasing

    Between Dordrecht and Lage Zwaluwe the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:00 AM hours.

    Advice

    Express buses are still running between Dordrecht and Lage Zwaluwe.
    Taxi's are available between Dordrecht and Dordrecht Zuid.

  3. Update

    Between Dordrecht and Lage Zwaluwe no trains are running due to over-running engineering works.
    This will take until approximately 10:00 AM hours.

    Advice

    Express buses are running between Dordrecht and Lage Zwaluwe.
    Taxi's are available between Dordrecht and Dordrecht Zuid.

    Train measures

    • Intercity 1900 Dordrecht - Eindhoven C. is cancelled between Dordrecht and Eindhoven Centraal
    • Intercity 2200 Dordrecht - Roosendaal is cancelled between Dordrecht and Roosendaal
    • Sprinter 5900 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
    • Sprinter 6600 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
  4. Update

    Between Dordrecht and Lage Zwaluwe no trains are running due to over-running engineering works.
    This will take until approximately 10:30 AM hours.

    Advice

    Express buses are running between Dordrecht and Lage Zwaluwe.
    Taxi's are available between Dordrecht and Dordrecht Zuid.

    Train measures

    • Intercity 1900 Dordrecht - Eindhoven C. is cancelled between Dordrecht and Eindhoven Centraal
    • Intercity 2200 Dordrecht - Roosendaal is cancelled between Dordrecht and Roosendaal
    • Sprinter 5900 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
    • Sprinter 6600 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
  5. Update

    Between Dordrecht and Lage Zwaluwe no trains are running due to over-running engineering works.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 1900 Dordrecht - Eindhoven C. is cancelled between Dordrecht and Eindhoven Centraal
    • Intercity 2200 Dordrecht - Roosendaal is cancelled between Dordrecht and Roosendaal
    • Sprinter 5900 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
    • Sprinter 6600 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
  6. Update

    Between Dordrecht and Lage Zwaluwe no trains are running due to over-running engineering works.
    This will take until approximately 10:00 AM hours.

    Train measures

    • Intercity 1900 Dordrecht - Eindhoven C. is cancelled between Dordrecht and Eindhoven Centraal
    • Intercity 2200 Dordrecht - Roosendaal is cancelled between Dordrecht and Roosendaal
    • Sprinter 5900 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
    • Sprinter 6600 Dordrecht - Lage Zwaluwe is cancelled between Dordrecht and Lage Zwaluwe
  7. Disruption

    Between Dordrecht and Lage Zwaluwe no trains are running due to over-running engineering works.
    This will take until approximately 10:00 AM hours.

More about this disruption

Statistics

This disruption started at 4:09 AM on August 18, 2021 and took 5 hours, 48 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights