Signalling and points failure: Heerlen-Maastricht (4 June 2021)
-
Disruption resolved Last update
Between Maastricht and Valkenburg the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Maastricht and Heerlen there are delays and fewer trains are running due to a signalling and points failure.
It is not known yet how long this will take.
Location of this disruption
This disruption is between Maastricht and Valkenburg.
See the disruptions map for a live overview of all disruptions in the Netherlands.
More about this disruption
Statistics
This disruption started at 2:56 PM on June 4, 2021 and took 9 hours, 1 minute in total.
For statistics, this disruption is caused due to a signalling and points failure.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.