sein- en wisselstoring

Large signalling and points failure: Rotterdam Centraal (31 May 2021)

  1. Disruption resolved Last update

    From and to Rotterdam Centraal the train traffic is fully resumed.

  2. Update

    From and to Rotterdam Centraal there are fewer trains running due to a large signalling and points failure.
    The extra travel time may be up to 15 minutes.
    Service is normal around 9:32 PM hours.

  3. Update

    From and to Rotterdam Centraal there are fewer trains running due to a large signalling and points failure.
    The extra travel time may be up to 15 minutes.
    Service is normal around 9:30 PM hours.

  4. Update

    From and to Rotterdam Centraal there are fewer trains running due to a large signalling and points failure.
    The extra travel time may be up to 30 minutes.
    Service is normal around 9:30 PM hours.

  5. Update

    From and to Rotterdam Centraal far fewer trains are running due to a large signalling and points failure.
    The extra travel time may be up to 60 minutes.
    Service is normal around 9:30 PM hours.

  6. Update

    From and to Rotterdam Centraal far fewer trains are running due to a large signalling and points failure.
    The extra travel time may be up to 60 minutes.
    Service is normal around 9:20 PM hours.

  7. Update

    From and to Rotterdam Centraal no trains are running due to a large signalling and points failure.
    The extra travel time may be up to 120 minutes.
    This will take until at least 5:00 PM hours.

  8. Update

    From and to Rotterdam Centraal no trains are running due to a large signalling and points failure.
    The extra travel time may be up to 120 minutes.
    This will take until at least 4:30 PM hours.

  9. Update

    From and to Rotterdam Centraal no trains are running due to a large signalling and points failure.
    This will take until at least 4:30 PM hours.

  10. Disruption

    From and to Rotterdam Centraal no trains are running due to a large signalling and points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 2:21 PM on May 31, 2021 and took 7 hours, 13 minutes in total.

For statistics, this disruption is caused due to a large signalling and points failure.

Operators

This disruption affects trains operated by NS, NS International, Thalys and Eurostar.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights