defecte spoorbrug

Damaged railway bridge: Utrecht-Rotterdam; Utrecht-Den Haag (24 February 2021)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Den Haag Centraal the train traffic is fully resumed.
    Between Utrecht Centraal and Rotterdam Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Rotterdam Centraal the restrictions are resolved.
    Between Utrecht Centraal and Den Haag Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 1:00 AM on Thursday, February 25, 2021.

  3. Update

    Between Utrecht Centraal and Den Haag Centraal far fewer trains are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal far fewer trains are running due to a damaged railway bridge.
    This will take until approximately 1:00 AM on Thursday, February 25, 2021.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Tiel
    • Sprinter 8600 Gouda - Alphen a/d Rijn keeps running normally between Gouda and Alphen a/d Rijn
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  4. Update

    Between Utrecht Centraal and Den Haag Centraal far fewer trains are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal far fewer trains are running due to a damaged railway bridge.
    This will take until approximately 1:00 AM on Thursday, February 25, 2021.

  5. Update

    Between Utrecht Centraal and Rotterdam Centraal there are delays and fewer trains are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal there are delays and fewer trains are running due to a damaged railway bridge.
    This will take until approximately 1:00 AM on Thursday, February 25, 2021.

  6. Update

    Between Utrecht Centraal and Rotterdam Centraal no trains are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal no trains are running due to a damaged railway bridge.
    This will take until approximately 1:00 AM on Thursday, February 25, 2021.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel is cancelled between Den Haag Centraal and Tiel
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  7. Update

    Between Utrecht Centraal and Rotterdam Centraal far fewer trains are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal far fewer trains are running due to a damaged railway bridge.
    This will take until approximately 1:00 AM on Thursday, February 25, 2021.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Tiel
    • Sprinter 8600 Gouda - Alphen a/d Rijn keeps running normally between Gouda and Alphen a/d Rijn
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  8. Update

    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 1:00 AM on Thursday, February 25, 2021.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Tiel
    • Sprinter 8600 Gouda - Alphen a/d Rijn keeps running normally between Gouda and Alphen a/d Rijn
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  9. Update

    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 10:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Tiel
    • Sprinter 8600 Gouda - Alphen a/d Rijn keeps running normally between Gouda and Alphen a/d Rijn
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  10. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 10:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Gouda
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  11. Update

    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Gouda
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  12. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 6:45 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Gouda
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  13. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:45 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Gouda
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  14. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Gouda
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  15. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel has a changed schedule between Den Haag Centraal and Gouda
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  16. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:30 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Tiel
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  17. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest keeps running normally between Rotterdam Centraal and Uitgeest
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel keeps running normally between Den Haag Centraal and Tiel
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  18. Update

    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  19. Update

    Between Utrecht Centraal and Rotterdam Centraal no intercities are running due to a damaged railway bridge.
    Between Utrecht Centraal and Den Haag Centraal no intercities are running due to a damaged railway bridge.
    This will take until approximately 5:00 PM hours.

  20. Update

    From and to Gouda there are delays and fewer trains are running due to a damaged railway bridge.
    This will take until approximately 5:00 PM hours.

  21. Update

    From and to Gouda there is a service disruption due to a damaged railway bridge.
    This will take until approximately 5:00 PM hours.

  22. Disruption

    From and to Gouda there is a service disruption due to a damaged railway bridge.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 3:03 PM on February 24, 2021 and took 8 hours, 56 minutes in total.

For statistics, this disruption is caused due to a damaged railway bridge.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights