Over-running engineering works: Rotterdam-Breda (HSL) (3 August 2020)
-
Disruption resolved Last update
Between Rotterdam Centraal and Breda the train traffic is fully resumed.
Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
- Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi keeps running normally between Amsterdam Centraal and Brussel-Zuid/Midi
-
Update
Between Rotterdam Centraal and Breda fewer trains are running on the high-speed line due to over-running engineering works.
This will take until approximately 11:00 AM hours.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
- Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi keeps running normally between Amsterdam Centraal and Brussel-Zuid/Midi
-
Update
Between Rotterdam Centraal and Breda fewer trains are running on the high-speed line due to over-running engineering works.
This will take until approximately 10:30 AM hours.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
- Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi keeps running normally between Amsterdam Centraal and Brussel-Zuid/Midi
-
Update
Between Rotterdam Centraal and Breda fewer Intercity direct trains are running due to over-running engineering works.
This will take until approximately 10:30 AM hours.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
- Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi keeps running normally between Amsterdam Centraal and Brussel-Zuid/Midi
-
Update
Between Rotterdam Centraal and Breda no Intercity Direct trains are running due to over-running engineering works.
This will take until approximately 10:30 AM hours.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
-
Update
Between Rotterdam Centraal and Breda no Intercity Direct trains are running due to over-running engineering works.
This will take until approximately 11:00 AM hours.Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
-
Disruption resolved
Between Rotterdam Centraal and Breda the train traffic is fully resumed.
Train measures
- Intercity direct 900 Amsterdam C. - Schiphol Airport - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Breda
More about this disruption
Statistics
This disruption started at 6:16 AM on August 3, 2020 and took 4 hours, 7 minutes in total.
For statistics, this disruption is caused due to over-running engineering works.
Operators
This disruption affects trains operated by NS and NS International.
Got delayed due to this disruption? You may be reimbursed.