Large signalling and points failure: Venlo-Roermond (25 June 2020)

  1. Disruption resolved Last update

    Between Swalmen and Roermond the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Swalmen and Roermond no trains are running due to a large signalling and points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 7:30 PM hours.

    Advice

    Local buses are running between Venlo, Tegelen, Reuver and Swalmen.
    Please postpone your journey when possible.

Location of this disruption

This disruption is between Swalmen and Roermond.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 5:58 PM on June 25, 2020 and took 6 hours, 52 minutes in total.

For statistics, this disruption is caused due to a large signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.