beschadigde spoorbrug

Damaged railway bridge: Apeldoorn-Zutphen (12 June 2020)

  1. Disruption resolved Last update

    Between Klarenbeek and Zutphen the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Zutphen and Klarenbeek no trains are running due to a damaged railway bridge.
    This will take until approximately 3:00 PM hours.

Location of this disruption

This disruption is between Klarenbeek and Zutphen.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 1:17 PM on June 12, 2020 and took 1 hour, 30 minutes in total.

For statistics, this disruption is caused due to a damaged railway bridge.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights