stroomstoring

Power failure: Arnhem-Duisburg-Düsseldorf (8 December 2019)

  1. Disruption resolved Last update

    Between Zevenaar and Emmerich the train traffic is fully resumed.

  2. Delays decreasing

    Between Zevenaar and Emmerich the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 10:30 AM hours.

  3. Update

    Between Zevenaar and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:00 AM hours.

    Advice

    Local buses are running between Zevenaar, Elten and Emmerich.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Zevenaar and Emmerich
  4. Update

    Between Zevenaar and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

    Advice

    Local buses are running between Zevenaar, Elten and Emmerich.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Zevenaar and Emmerich
  5. Update

    Between Zevenaar and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

    Advice

    Express buses are running between Zevenaar and Emmerich.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Zevenaar and Emmerich
  6. Update

    Between Zevenaar and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Zevenaar and Emmerich
  7. Update

    Between Arnhem Centraal and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Arnhem Centraal and Zevenaar
  8. Update

    Between Arnhem Centraal and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:30 AM hours.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Arnhem Centraal and Zevenaar
  9. Update

    Between Arnhem Centraal and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

    Train measures

    • Sneltrein 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Arnhem Centraal and Zevenaar
  10. Update

    Between Arnhem Centraal and Emmerich there are no trains running due to a power failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

  11. Update

    Between Arnhem Centraal and Emmerich there are no trains running due to a signal failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:45 AM hours.

  12. Disruption

    Between Arnhem Centraal and Emmerich there is a service disruption due to a power failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:49 AM on December 8, 2019 and took 3 hours, 22 minutes in total.

For statistics, this disruption is caused due to a power failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS International, Deutsche Bahn and Abellio.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights