Over-running engineering works: Schiphol-Lelystad; Schiphol-Amersfoort (28 June 2019)
-
Disruption resolved Last update
Between Amsterdam RAI and Duivendrecht the train traffic is fully resumed.
- Show complete timeline…
-
Disruption reported
Between Amsterdam RAI and Duivendrecht there is a service disruption due to over-running engineering works.
Updates will follow as more information becomes available.
Location of this disruption
This disruption is between Amsterdam RAI and Duivendrecht.
See the disruptions map for a live overview of all disruptions in the Netherlands.
More about this disruption
Statistics
This disruption started at 5:31 AM on June 28, 2019 and took 39 minutes in total.
For statistics, this disruption is caused due to over-running engineering works.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.