stroomstoring

Power failure: Groningen-Bad Nieuweschans; Groningen-Veendam (5 October 2018)

  1. Disruption resolved Last update

    Between Groningen and Groningen Europapark the train traffic is fully resumed.

  2. Delays decreasing

    Between Groningen and Groningen Europapark the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 3:00 PM hours.

  3. Update

    Between Groningen and Groningen Europapark there are no trains running due to a power failure.
    This will take until approximately 2:45 PM hours.

    Advice

    Buses are running between Groningen and Groningen Europapark.

    Train measures

    • Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Groningen and Groningen Europapark
    • Stoptrein 37800 Groningen - Veendam is cancelled between Groningen and Groningen Europapark
  4. Update

    Between Groningen and Groningen Europapark there are no trains running due to a power failure.
    This will take until approximately 2:45 PM hours.

    Train measures

    • Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Groningen and Groningen Europapark
    • Stoptrein 37800 Groningen - Veendam is cancelled between Groningen and Groningen Europapark
  5. Update

    Between Groningen and Groningen Europapark there are no trains running due to a power failure.
    This will take until approximately 2:15 PM hours.

    Train measures

    • Stoptrein 37500 Groningen - Winschoten - Bad Nieuweschans is cancelled between Groningen and Groningen Europapark
    • Stoptrein 37800 Groningen - Veendam is cancelled between Groningen and Groningen Europapark
  6. Update

    Between Groningen and Groningen Europapark there are no trains running due to a power failure.
    This will take until approximately 2:15 PM hours.

  7. Disruption

    Between Groningen and Groningen Europapark there are no trains running due to a power failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 12:00 PM on October 5, 2018 and took 2 hours, 53 minutes in total.

For statistics, this disruption is caused due to a power failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights