A new timetable will be introduced on Sunday, December 9. More information about the 2018 timetable

Disruption Utrecht-Rotterdam

Power failure
This disruption is resolved.

Current travel advice

Between Utrecht Centraal and Rotterdam Centraal the train traffic is fully resumed.

Mar 23, 2018 8:30 PM

Earlier messages

Between Utrecht Centraal and Rotterdam Centraal the restrictions are resolved.
Delays are diminishing.
Service is normal around 8:30 PM hours.

Mar 23, 2018 8:09 PM

Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a power failure.
The extra travel time is about 15 minutes.
This will take until approximately 8:30 PM hours.

Train measures

  • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Gouda and Utrecht Centraal
  • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
  • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
  • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Gouda Goverwelle and Breukelen
  • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda Goverwelle
  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Woerden and Utrecht Centraal
  • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Woerden and Utrecht Centraal
  • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Gouda and Utrecht Centraal
Mar 23, 2018 7:54 PM

Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a power failure.
The extra travel time is about 15 minutes.
This will take until at least 8:30 PM hours.

Mar 23, 2018 7:22 PM

Between Utrecht Centraal and Rotterdam Centraal fewer intercities are running due to a power failure.
The extra travel time is about 15 minutes.
This will take until at least 8:00 PM hours.

Mar 23, 2018 6:53 PM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 6:53 PM on March 23, 2018 and took 1 hour, 37 minutes in total.

For statistics, this disruption is caused due to a power failure.