inzet brandweer

Deployment of the fire department: Venlo (11 January 2018)

  1. Disruption resolved Last update

    From and to Venlo the train traffic is fully resumed.

  2. Delays decreasing

    From and to Venlo the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 7:30 PM hours.

  3. Update

    From and to Venlo there are no trains running due to deployment of the fire department.
    This will take until approximately 7:30 PM hours.

    Advice

    Buses are running between Tegelen and Blerick.
    Buses are running between Venlo and Blerick.

    Train measures

    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Venlo is cancelled between Blerick and Venlo
    • RE 19 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Venlo and Kaldenkirchen
    • Stoptrein 32200 Nijmegen - Roermond is cancelled between Blerick and Tegelen
    • Stoptrein 32300 Nijmegen - Boxmeer is cancelled between Venray and Venlo
  4. Update

    From and to Venlo there are no trains running due to deployment of the fire department.
    This will take until approximately 7:30 PM hours.

    Advice

    Buses are running between Venlo and Blerick.

    Train measures

    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Venlo is cancelled between Blerick and Venlo
    • RE 19 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Venlo and Kaldenkirchen
    • Stoptrein 32200 Nijmegen - Roermond is cancelled between Blerick and Tegelen
    • Stoptrein 32300 Nijmegen - Boxmeer is cancelled between Venray and Venlo
  5. Update

    From and to Venlo there are no trains running due to deployment of the fire department.
    This will take until approximately 7:30 PM hours.

    Train measures

    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Venlo is cancelled between Blerick and Venlo
    • RE 19 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Venlo and Kaldenkirchen
    • Stoptrein 32200 Nijmegen - Roermond is cancelled between Blerick and Tegelen
    • Stoptrein 32300 Nijmegen - Boxmeer is cancelled between Venray and Venlo
  6. Update

    From and to Venlo there are no trains running due to deployment of the fire department.
    It is not known yet how long this will take.

    Train measures

    • Intercity 3500 Schiphol Airport - Utrecht C. - Eindhoven - Venlo is cancelled between Blerick and Venlo
    • RE 19 20000 Arnhem C. - Duisburg Hbf - Düsseldorf Hbf is cancelled between Venlo and Kaldenkirchen
    • Stoptrein 32200 Nijmegen - Roermond is cancelled between Blerick and Tegelen
    • Stoptrein 32300 Nijmegen - Boxmeer is cancelled between Venray and Venlo
  7. Update

    From and to Venlo there are no trains running due to deployment of the fire department.
    It is not known yet how long this will take.

  8. Update

    From and to Venlo there is a service disruption due to an emergency call.
    It is not known yet how long this will take.

  9. Disruption

    From and to Venlo there is a service disruption due to an emergency call.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 4:51 PM on January 11, 2018 and took 2 hours, 23 minutes in total.

For statistics, this disruption is caused due to deployment of the fire department.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS, Arriva and eurobahn.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights