  1. Disruption resolved Last update

    Between Gouda and Rotterdam Centraal the train traffic is fully resumed.
    Between Gouda and Den Haag Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Gouda and Rotterdam Centraal the restrictions are resolved.
    Between Gouda and Den Haag Centraal the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 5:00 PM hours.

  3. Update

    Between Gouda and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    Between Gouda and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    Service is normal around 5:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Gouda and Woerden
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda
    • Sprinter 7700 Rotterdam C. - Gouda Goverwelle is cancelled between Rotterdam Centraal and Gouda
    • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Woerden
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  4. Update

    Between Gouda and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    Between Gouda and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Gouda and Woerden
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda
    • Sprinter 7700 Rotterdam C. - Gouda Goverwelle is cancelled between Rotterdam Centraal and Gouda
    • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Woerden
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  5. Update

    Between Gouda and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    Between Gouda and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    This will take until approximately 4:15 PM hours.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Gouda and Woerden
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda
    • Sprinter 7700 Rotterdam C. - Gouda Goverwelle is cancelled between Rotterdam Centraal and Gouda
    • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Woerden
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  6. Update

    Between Gouda and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    Between Gouda and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    It is not known yet how long this will take.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Gouda and Woerden
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda
    • Sprinter 7700 Rotterdam C. - Gouda Goverwelle is cancelled between Rotterdam Centraal and Gouda
    • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Woerden
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  7. Update

    Between Gouda and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    Between Gouda and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    It is not known yet how long this will take.

    Train measures

    • Intercity 500 Rotterdam C. - Utrecht C. - Zwolle - Groningen is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 600 Rotterdam C. - Utrecht C. - Zwolle - Leeuwarden is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Intercity 1700 Den Haag C. - Amersfoort - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2000 Den Haag C. - Utrecht C. is cancelled between Den Haag Centraal and Utrecht Centraal
    • Intercity 2800 Rotterdam C. - Utrecht C. is cancelled between Rotterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Gouda and Woerden
    • Sprinter 6800 Den Haag C. - Gouda Goverwelle is cancelled between Den Haag Centraal and Gouda
    • Sprinter 7700 Rotterdam C. - Gouda Goverwelle is cancelled between Rotterdam Centraal and Gouda
    • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Woerden
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal
  8. Update

    Between Gouda and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    Between Gouda and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    It is not known yet how long this will take.

  9. Update

    Between Utrecht Centraal and Rotterdam Centraal far fewer trains are running due to over-running engineering works.
    Between Utrecht Centraal and Den Haag Centraal far fewer trains are running due to over-running engineering works.
    It is not known yet how long this will take.

  10. Disruption

    Between Utrecht Centraal and Den Haag Centraal there are no trains running due to over-running engineering works.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 6:04 AM on November 27, 2017 and took 10 hours, 55 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights