Over-running engineering works: Amsterdam-Rotterdam-Breda (HSL) (20 October 2017)
-
Disruption resolved Last update
Between Schiphol Airport and Breda the train traffic is fully resumed.
-
Delays decreasing
Between Schiphol Airport and Breda the restrictions are resolved.
Delays are decreasing.
This will take until approximately 7:00 AM hours. -
Disruption reported
Between Schiphol Airport and Breda no Intercity Direct trains are running due to over-running engineering works.
It is not known yet how long this will take.
Location of this disruption
This disruption is between Schiphol Airport and Breda.
More about this disruption
Statistics
This disruption started at 6:14 AM on October 20, 2017 and took 45 minutes in total.
For statistics, this disruption is caused due to over-running engineering works.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS, NS International and Thalys.
Got delayed due to this disruption? You may be reimbursed.