uitloop werkzaamheden

Over-running engineering works: Zaandam-Enkhuizen (10 July 2017)

  1. Disruption resolved Last update

    Between Hoorn Kersenboogerd and Enkhuizen the train traffic is fully resumed.

  2. Show complete timeline…
  3. Disruption reported

    Between Hoorn Kersenboogerd and Enkhuizen no trains are running due to over-running engineering works.
    This will take until approximately 1:00 PM hours.

    Train measures

    • Sprinter 3300 Kersenboogerd - Zaandam - Schiphol Airport - Leiden C. is cancelled between Enkhuizen and Hoorn Kersenboogerd (only in direction of Hoorn Kersenboogerd)
    • Intercity 4500 Enkhuizen - Zaandam - Amsterdam C. is cancelled between Enkhuizen and Hoorn Kersenboogerd
    • Intercity 14500 Amsterdam C. - Enkhuizen is cancelled between Enkhuizen and Hoorn

Location of this disruption

This disruption is between Hoorn Kersenboogerd and Enkhuizen.

Map of the location of this disruption

More about this disruption

Statistics

This disruption started at 3:07 AM on July 10, 2017 and took 8 hours, 8 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.