Points failure: Leiden-Duivendrecht-Lelystad (18 April 2017)

  1. Disruption resolved Last update

    Between Lelystad Centrum and Leiden Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Lelystad Centrum and Leiden Centraal the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 7:30 AM hours.

  3. Update

    Between Lelystad Centrum and Leiden Centraal there are fewer trains running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until at least 8:00 AM hours.

    Train measures

    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Vlissingen and Leiden Centraal
  4. Update

    Between Lelystad Centrum and Leiden Centraal there are fewer trains running due to a points failure.
    The extra travel time may be up to 15 minutes.
    This will take until at least 8:00 AM hours.

  5. Disruption

    Between Lelystad Centrum and Leiden Centraal there are fewer trains running due to a points failure.
    The extra travel time may be up to 15 minutes.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 5:51 AM on April 18, 2017 and took 1 hour, 42 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.