Disruption Gouda-Den Haag

An earlier disruption
This disruption is resolved.

Current travel advice

Between Gouda and Den Haag Centraal the train traffic is fully resumed.

Feb 25, 2017 6:59 PM

Earlier messages

Between Gouda and Den Haag Centraal the restrictions are resolved.
Delays are diminishing.
Service is normal around 7:00 PM hours.

Feb 25, 2017 6:45 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to an earlier disruption.
The extra travel time may be up to 60 minutes.
This will take until approximately 7:00 PM hours.

Advice

Use the tram between Zoetermeer and Den Haag Centraal.

Train measures

  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Den Haag Centraal (only in direction of Den Haag Centraal)
Feb 25, 2017 6:04 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to an earlier disruption.
The extra travel time is more than 60 minutes.
This will take until approximately 7:00 PM hours.

Advice

Use the tram between Zoetermeer and Den Haag Centraal.

Train measures

  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Den Haag Centraal (only in direction of Den Haag Centraal)
Feb 25, 2017 5:54 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
Service is normal around 6:15 PM hours.

Advice

Use the tram between Zoetermeer and Den Haag Centraal.
Local buses are running between Gouda, Zoetermeer Oost and Zoetermeer.

Train measures

  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Den Haag Centraal
Feb 25, 2017 5:34 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until at least 6:15 PM hours.

Advice

Use the tram between Zoetermeer and Den Haag Centraal.
Local buses are running between Gouda, Zoetermeer Oost and Zoetermeer.

Train measures

  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Den Haag Centraal
Feb 25, 2017 5:19 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 6:15 PM hours.

Advice

Use the tram between Zoetermeer and Den Haag Centraal.

Train measures

  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Den Haag Centraal
Feb 25, 2017 4:52 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 6:15 PM hours.

Train measures

  • Sprinter 7800 Den Haag C. - Utrecht C. is cancelled between Gouda and Den Haag Centraal
Feb 25, 2017 4:42 PM

Between Gouda and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 6:15 PM hours.

Feb 25, 2017 4:30 PM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 4:30 PM on February 25, 2017 and took 2 hours, 29 minutes in total.

For statistics, this disruption is caused due to a points failure.