eerdere verstoring

An earlier disruption: Gouda-Den Haag; Leiden-Den Haag C; Den Haag-Rotterdam (31 January 2017)

  1. Disruption resolved Last update

    From and to Den Haag Centraal the train traffic is fully resumed.

  2. Delays decreasing

    From and to Den Haag Centraal the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 7:30 AM hours.

  3. Update

    From and to Den Haag Centraal there are fewer trains running due to an earlier disruption.
    The extra travel time is more than 30 minutes.
    This will take until approximately 7:30 AM hours.

  4. Update

    From and to Den Haag Centraal there are fewer trains running due to an earlier disruption.
    The extra travel time is about 30 minutes.
    This will take until approximately 7:30 AM hours.

  5. Delays decreasing

    From and to Den Haag Centraal the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 6:00 AM hours.

  6. Update

    From and to Den Haag Centraal there are no trains running due to over-running engineering works.
    The extra travel time is more than 60 minutes.
    It is not known yet how long this will take.

  7. Disruption

    Between Leiden Centraal and Den Haag Centraal far fewer trains are running due to a points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 5:11 AM on January 31, 2017 and took 2 hours, 21 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights