Disruption Amersfoort-Ede-Wageningen

Overhead wires covered with frost
This disruption is resolved.

Current travel advice

Between Ede-Wageningen and Barneveld Zuid the train traffic is fully resumed.

Jan 15, 2017 8:28 AM

Earlier messages

Between Ede-Wageningen and Barneveld Zuid the restrictions are resolved.
Delays are diminishing.
Service is normal around 8:30 AM hours.

Jan 15, 2017 8:16 AM

Between Ede-Wageningen and Barneveld Zuid there are fewer trains running due to overhead wires covered with frost.
The extra travel time may be up to 30 minutes.
It is not known yet how long this will take.

Jan 15, 2017 7:54 AM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Connexxion.

Information

This disruption started at 7:53 AM on January 15, 2017 and took 35 minutes in total.

For statistics, this disruption is caused due to overhead wires covered with frost.