Disruption Lelystad-Zwolle

Ice formation on the overhead wires
This disruption is resolved.

Current travel advice

Between Lelystad Centrum and Zwolle the train traffic is fully resumed.

Jan 7, 2017 4:42 PM

Earlier messages

Between Lelystad Centrum and Zwolle the restrictions are resolved.
Delays are diminishing.
Service is normal around 4:45 PM hours.

Jan 7, 2017 4:26 PM

Between Lelystad Centrum and Zwolle there are no trains running due to ice formation on the overhead wires.
This will take until at least 5:00 PM hours.

Advice

Local buses are running between Zwolle, Kampen Zuid, Dronten and Lelystad Centrum.

Train measures

  • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
  • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  • Sprinter 4600 Den Haag C. - Lelystad C. - Amsterdam CS - Zwolle is cancelled between Lelystad Centrum and Zwolle
Jan 7, 2017 3:42 PM

Between Lelystad Centrum and Zwolle there are no trains running due to ice formation on the overhead wires.
Service is normal around 5:00 PM hours.

Advice

Local buses are running between Zwolle, Kampen Zuid, Dronten and Lelystad Centrum.

Train measures

  • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
  • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  • Sprinter 4600 Den Haag C. - Lelystad C. - Amsterdam CS - Zwolle is cancelled between Lelystad Centrum and Zwolle
Jan 7, 2017 3:35 PM

Between Lelystad Centrum and Zwolle there are no trains running due to ice formation on the overhead wires.
This will take until at least 5:00 PM hours.

Advice

Local buses are running between Zwolle, Kampen Zuid, Dronten and Lelystad Centrum.

Train measures

  • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
  • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  • Sprinter 4600 Den Haag C. - Lelystad C. - Amsterdam CS - Zwolle is cancelled between Lelystad Centrum and Zwolle
Jan 7, 2017 3:11 PM

Between Lelystad Centrum and Zwolle there are no trains running due to ice formation on the overhead wires.
This will take until at least 4:00 PM hours.

Advice

Local buses are running between Zwolle, Kampen Zuid, Dronten and Lelystad Centrum.

Train measures

  • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
  • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  • Sprinter 4600 Den Haag C. - Lelystad C. - Amsterdam CS - Zwolle is cancelled between Lelystad Centrum and Zwolle
Jan 7, 2017 2:07 PM

Between Lelystad Centrum and Zwolle there are no trains running due to ice formation on the overhead wires.
This will take until at least 2:30 PM hours.

Advice

Local buses are running between Zwolle, Kampen Zuid, Dronten and Lelystad Centrum.

Train measures

  • Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
  • Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
  • Sprinter 4600 Den Haag C. - Lelystad C. - Amsterdam CS - Zwolle is cancelled between Lelystad Centrum and Zwolle
Jan 7, 2017 12:55 PM

Between Lelystad Centrum and Zwolle there are no trains running due to ice formation on the overhead wires.
It is not known yet how long this will take.

Jan 7, 2017 9:34 AM

Between Lelystad Centrum and Zwolle there are fewer trains running due to a broken down train.
It is not known yet how long this will take.

Jan 7, 2017 9:27 AM

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Information

This disruption started at 9:26 AM on January 7, 2017 and took 7 hours, 16 minutes in total.

For statistics, this disruption is caused due to ice formation on the overhead wires.