Points failure: Utrecht-Gouda (7 January 2017)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Gouda Goverwelle the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Gouda Goverwelle the restrictions are resolved.
    Delays are diminishing.
    Service is normal around 12:30 PM hours.

  3. Update

    Between Utrecht Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
    Service is normal around 12:30 PM hours.

  4. Update

    Between Utrecht Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
    It is not known yet how long this will take.

  5. Disruption

    Between Utrecht Centraal and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
    Between Gouda Goverwelle and Rotterdam Centraal fewer Sprinter trains are running due to a points failure.
    It is not known yet how long this will take.

More about this disruption

Statistics

This disruption started at 7:02 AM on January 7, 2017 and took 5 hours, 27 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.